What a Full Kitchen Remodel in Vineyards Actually Costs and How Long It Takes
A full kitchen remodel in Vineyards, FL typically runs between $14,000 and $45,000 and takes six to ten weeks from the first day of demolition to final walkthrough. That range covers taking a kitchen down to the studs, replacing everything from flooring and drywall to cabinets, countertops, appliances, lighting, and plumbing fixtures, with the final number hinging largely on how much you move the sink and stove, the cabinet line and countertop material you choose, and whether load-bearing walls come out. Call us at (844) 638-7249 for a free, written on-site estimate with line-by-line pricing, not a single vague bottom-line number you can’t trust.
The Real Sequence of a Full Kitchen Remodel in Vineyards
Most homeowners haven’t lived through a gut renovation before, so the timeline can feel abstract until you see it broken into real stages. Here is how we run this job in Vineyards, week by week, and what you need to decide at each handoff.
Stage 1: Demolition, Rough-In, and the First Inspection (Days 1-5)
We contain the worksite with floor-to-ceiling plastic barriers to keep dust out of the rest of the house, then strip the kitchen down to bare studs and subfloor. Any non-load-bearing walls scheduled for removal come out on day one. Our electricians and plumbers rough in new wiring, outlets, switch legs, water lines, and drain locations to match the final layout, and we schedule the first rough-in inspection with Collier County the moment the walls are open. If you’re moving the sink or range more than a few feet, the plumbing re-route and any electrical panel work happen here, and that scope is a major cost driver you will already have seen in your estimate, never a surprise change order.
Stage 2: Insulation, Drywall, and Floor Prep (Days 6-14)
Once the rough inspection is signed off, we insulate exterior walls to current Florida Building Code, hang and finish drywall to a level-five surface where needed, and float the floor. In most Vineyards homes built in the late ’80s and early ’90s, we are working on a concrete slab, which means any plumbing chases trenched into the floor get backfilled and leveled before tile or hardwood underlayment goes down. This is also when you’ll confirm your flooring material, grout color, and any accent-tile layouts.
Stage 3: Cabinets, Trim, and Countertop Templating (Days 15-25)
Cabinet boxes go in first and get shimmed level on Vineyards’ often slightly-settled slabs, then doors, drawer fronts, and crown molding. Once the base cabinets are locked in, a fabricator comes out to digitally template your countertops. Natural stone and quartz lead times run one to three weeks depending on the slab, so we sequence this early to avoid dead days downstream. Your decisions here include cabinet hardware, sink style, and the edge profile on the stone.
Stage 4: Finishes, Trim, and Appliance Hookups (Days 26-40)
Countertops are installed, plumbing fixtures get connected, and the backsplash goes in with any feature tile behind the range. Electricians return to install under-cabinet lighting, pendant fixtures over the island, and all switch and outlet covers. Appliances get set, leveled, and tested. In a permitted kitchen remodel, the county requires a final electrical and plumbing inspection at this stage before the walls are considered closed and the job signed off.
Stage 5: Punch List and Final Walkthrough (Days 41-48)
Paint touch-ups, cabinet alignment, drawer-glide adjustments, caulk and grout seal, filter and disposal test. The last week is detail work. You walk the kitchen with our project lead, flag anything that doesn’t sit right, and we fix it before we call the job complete. This is not an afterthought; it is how we honor the 730-Day Done Right Promise on every full kitchen remodel we do in Vineyards.
The Choices That Shape Your Full Kitchen Remodel
Every full kitchen remodel sits on a spectrum between “factory-stock replacement” and “custom millwork with relocated plumbing.” Here are the spec decisions that determine where your job lands.
- Cabinet construction and finish. Stock thermofoil or melamine cabinets keep the budget lean; plywood-box, soft-close, painted-finish lines from makers like KraftMaid push into the mid-to-upper range. Fully custom inset cabinetry with dovetailed drawers and furniture-grade finishes sits at the high end. In Vineyards’ mid-’90s coach homes with smaller galley kitchens, mid-range cabinets usually deliver the best cost-to-value ratio.
- Countertop slab material. Laminate lands on the low end of the per-square-foot cost curve. Quartz and granite occupy the middle with good durability and a wide price spread depending on the slab tier. Marble and quartzite sit at the high end and require more maintenance. With Cambria and similar engineered quartz, you get a non-porous surface that holds up well against Florida humidity.
- Layout changes and load-bearing walls. Keeping the sink, dishwasher, and range in their original footprint is the single biggest cost-containment decision in any Vineyards kitchen remodel. Moving plumbing across the slab means trenching into concrete, running new drains, and sometimes upsizing vent stacks. Removing or modifying a load-bearing wall adds structural engineering, a beam spec, and a separate plan-review cycle with the county.
- Flooring material and substrate prep. Luxury vinyl plank and porcelain tile are the two most common choices for slab-on-grade Vineyards homes. Large-format tile requires a flatter floor and more labor per square foot. If you’re removing 30-year-old ceramic tile, we budget for possible slab grinding or self-leveler once the old thinset is chipped off.
- Appliance package and electrical load. Swapping a standard 30-inch electric range for a 36- or 48-inch gas or induction cooktop often means running a new gas line or a dedicated 50-amp circuit, plus makeup-air requirements for high-CFM hoods. These choices ripple into the rough-in scope, so we pin them down in the estimate, not after.
What a Full Kitchen Remodel Costs in Vineyards, FL
Most full kitchen remodels we price in Vineyards settle between $18,000 and $38,000, with the $14,000 low end representing a keep-the-footprint, stock-cabinet, laminate-countertop refresh and the $45,000 high end covering custom cabinetry, natural stone, relocated plumbing, structural work, and a full appliance upgrade. Here is what drives the spread.
Kitchen size, measured by linear feet of cabinetry and square feet of countertop, sets the baseline. A coach-home galley kitchen with 14 linear feet of cabinets costs less to outfit than a sprawling open-plan kitchen with 28 linear feet and a 9-foot island. The condition inside the walls matters: older Vineyards homes can hide corroded galvanized drain lines, undersized circuits, or wall framing that needs blocking for modern cabinet loads, and we budget for what experience tells us we are likely to find, not a best-case scenario.
Every written estimate from us includes a fixed line-by-line scope: demo, dumpster, rough plumbing and electrical, drywall and paint, cabinet and countertop installation, flooring, backsplash, trim, appliance hookups, and permit coordination with Collier County. What is typically not included unless you ask us to scope it are structural engineering reports for wall removal, appliance purchases themselves, and any remediation of pre-existing mold, asbestos, or water damage discovered behind the walls. We identify those items early in demolition so you always know the price of the next decision before you make it. Call (844) 638-7249 to schedule a free on-site estimate for your full kitchen remodel in Vineyards.
How Vineyards Specifically Shapes This Job
Vineyards is a master-planned, HOA-governed golf community in North Naples where most homes were built between the late 1980s and late 1990s, and that matters to a full kitchen remodel in two overlapping ways. First, these are concrete block and stucco homes on slabs, which means any plumbing relocation requires trenching into the floor, a step that eats more labor and time than it would in a pier-and-beam house and demands careful coordination with the rough-in inspection. Second, while an interior kitchen remodel does not require the Vineyards Community Association’s Architectural Review Board sign-off the way a window or roof replacement does, any kitchen job that touches exterior walls, vents new range hood ducting through a stucco wall, or changes a window opening crosses squarely into ARB territory. We flag that during the estimating walk so there are no stop-work surprises.
Collier County’s permit office will not issue a permit for structural, electrical, or plumbing work without a licensed contractor on file, and failed inspections over improperly strapped appliance circuits or undersized drain venting are common when a crew is not dialed into current FBC requirements. In a community squarely in the high-velocity hurricane zone, even an interior remodel must respect wind-load and electrical-grounding standards that some out-of-area contractors underestimate. Our team knows which inspectors cover Vineyards, what they flag most often, and how to sequence the sign-offs so your kitchen doesn’t sit half-finished waiting on a re-inspection.
Most kitchens we open up in Vineyards are 25 to 35 years old and have never been remodeled. That means we routinely find original electric-range circuits that are undersized for modern induction cooktops, galvanized drain arms that have thinned with age, and drywall that was not sealed behind the original builder-grade cabinets. We budget for these realities upfront because we have seen them in dozens of homes from the same era. A complementary project many homeowners in Vineyards consider alongside a kitchen overhaul is a Full Bathroom Remodeling in Vineyards, especially in split-floor-plan homes where the primary bath shares a wall with the kitchen plumbing stack, letting us consolidate the plumbing scope and reduce the total cost across both spaces.
If you are already planning a full Kitchen Remodeling in Vineyards project, it’s worth understanding that our Kitchen Remodeling crew includes dedicated cabinet installers, stone templating coordinators, and a project lead who is on-site at every critical handoff. Some homeowners take the opportunity while the kitchen is torn apart to have us reconfigure an adjacent bath, and we frequently see this paired with a Walk-In Showers & Shower Remodeling in Vineyards conversion that uses the same licensed plumbers and electricians already on site, keeping the total disruption shorter than scheduling the projects separately.
Serving Vineyards, FL - Our Local Coverage Area
We’re based in the Vineyards area and know this community well. Use the map below to see our service coverage - if you’re nearby, we can almost certainly help.
Frequently Asked - Full Kitchen Remodeling in Vineyards
Six to ten weeks is the realistic range for a down-to-the-studs gut remodel, from the first day of demolition to the final walkthrough. The exact duration depends on whether you are moving the sink or stove, the countertop material’s fabrication lead time, and how quickly Collier County processes the rough and final inspections. We set a written schedule at contract and update you every week, so you are never guessing when you can cook again.
Yes. Any kitchen remodel in Vineyards that touches electrical wiring, plumbing lines, structural walls, or new window or vent openings requires a permit pulled through Collier County. We handle the permit application, schedule the inspections, and make sure the work passes on the first trip. Skipping the permit puts you at risk with your insurance carrier and becomes a disclosure headache if you sell the house later.
If you keep the sink, dishwasher, and range in their current locations, the job typically falls between $14,000 and $25,000 depending on cabinet grade and countertop choice. That assumes no load-bearing walls come out and that the existing electrical panel has capacity for your new appliance package. Relocating plumbing and reconfiguring the layout is the single biggest cost variable in any full kitchen remodel, which is why we walk every homeowner through a budget-versus-footprint conversation before we finalize the estimate.
Our 730-Day Done Right Promise covers all workmanship on every full kitchen remodel we complete in Vineyards. That means if something isn’t right within two full years of the final walkthrough, we make it right at no cost to you. Manufacturer warranties on cabinets, countertops, appliances, and fixtures run parallel to our workmanship guarantee and vary by product line. We provide all warranty documentation in your close-out package so you know exactly what is covered and for how long.
Most homeowners do, but it’s a disruption, no question. We set up a temporary kitchen station with a microwave, coffee maker, and a utility sink when possible, and we contain the worksite with sealed plastic barriers to keep construction dust out of living areas. The toughest window is usually the week between countertop removal and new countertop installation, and we time the demo to minimize the days you are without a functional sink. For homeowners who would rather not live around the work, many in Vineyards plan the remodel around a trip or a seasonal move-out, which we schedule to.
Get a Written Estimate for Your Vineyards Full Kitchen Remodel
A full kitchen remodel is a significant investment, and you should not commit to a number until you have seen it broken down in writing. We walk your kitchen with you in Vineyards, talk through what you want to change and what you’d rather keep, and hand you a line-by-line estimate covering every trade, every material, and every permit fee before you sign anything. Call (844) 638-7249 to schedule that walk-through. We answer the phone live, 24/7, and the estimate is free with no obligation.
Written by Derek Hollenbeck, Owner at Groundwork Construction Co., serving Vineyards and Collier County.